Service Load Calculation

NEC 220.82 in plain terms — what counts, what does not, and the answer in amps.

What size electrical service for a 1800 sq ft house with an electric range and dryer?

1,800 ft², electric range and dryer, gas water heater
125 A minimum
calculated load 104 A · NEC minimum 125 A · 150 A is what usually gets installed
1,800 ft², electric range and dryer, gas water heater104 ACalculated load125 ANEC minimum servi…
Calculated load24,880 VA ÷ 240 V104A
NEC minimum servicethe next standard size at or above the calculated load125A
Commonly installedone size up — leaves 31% headroom for an EV charger or a heat pump later150A
General lighting1,800 ft² × 3 VA5,400VA
Small appliance + laundrytwo kitchen circuits and one laundry, 1,500 VA each4,500VA
Fixed appliancesthe most common configuration in US housing19,300VA
Before demand factor29,200VA
After demand factor100% of the first 10 kVA, 40% of the rest17,680VA
Heating or coolingthe larger of the two, not both — they do not run together7,200VA

Notes

  • **Do not add up the nameplates.** Every appliance in this house adds to 29,200 VA, but NEC 220.82 counts **100% of the first 10 kVA and 40% of everything above it** — because a house never runs the oven, the dryer, the dishwasher and the disposal at the same second. That single step is why the honest answer is 104 A and the forum answer is usually double.
  • **125 A is the code minimum; 150 A is what gets installed.** Services come in fixed sizes, so "you need 104 amps" is never an answer on its own. 125 A satisfies NEC for this load today. Most electricians fit 150 A anyway, because the marginal cost at install time is small and the cost of upgrading later — new meter base, new mast, utility coordination — is not.
  • **Heating and cooling count once, whichever is larger.** Adding both is the second most common error and it pushes plenty of ordinary houses onto a 400 A recommendation they will never need.
  • **Adding an EV charger later is the change most likely to break this.** A 48 A charger adds 11,520 VA before demand factors and is the single most common reason a service that was fine for thirty years suddenly is not.
  • Panel space is a separate constraint from service size. A 200 A panel with every slot full needs a subpanel or a tandem-breaker plan, and that has nothing to do with the calculation above. And a licensed electrician's stamped load calculation is what an inspector accepts — this page is for knowing where you stand before you call one.